Construction Planning And Management objective questions and answers


11.  A critical activity has


   A. Maximum float

   B. Minimum float

   C. Zero float

   D. Average float


✔ View Answer


C. Zero float

✍ Your Comments

Your name:

Your Email:

Your Comments:



12.  Residential buildings are treated as


   A. Light construction

   B. Heavy construction

   C. Industrial construction

   D. Private construction


✔ View Answer


A. Light construction

✍ Your Comments

Your name:

Your Email:

Your Comments:



13.  The estimated time required to perform an activity is known as


   A. Event

   B. Dummy

   C. Duration

   D. Float


✔ View Answer


C. Duration

✍ Your Comments

Your name:

Your Email:

Your Comments:



14.  Critical path lies along the activities having total float


   A. Positive

   B. Negative

   C. Zero

   D. Same


✔ View Answer


C. Zero

✍ Your Comments

Your name:

Your Email:

Your Comments:



15.  Railway projects are treated as


   A. Light construction

   B. Heavy construction

   C. Industrial construction

   D. None of the these


✔ View Answer


B. Heavy construction

✍ Your Comments

Your name:

Your Email:

Your Comments: