41. The standard deviation is
A. An average variation
B. Similar to the median
C. One half of the mode
D. A measure of dispersion
✔ View Answer
D. A measure of dispersion
✍ Your Comments
42. In a breakevent chart, abscissa represents
A. Constant expenses
B. Total expenses
C. Profits
D. Amount
✔ View Answer
✍ Your Comments
43. A duel event
A. Consumes zero time
B. Progress is simultaneously in two directions
C. Is any event other than the first and last events
D. Is the beginning of one event end end of another
✔ View Answer
✍ Your Comments
44. The time to complete the entire project corresponds to
A. The shortest path from initial node to final node
B. The longest path from initial node to final node
C. The sum of the distances from initial node to final node
D. The average of the time taken by all activities
✔ View Answer
✍ Your Comments
45. For completion of a project, the critical path of the network represents
A. Minimum time
B. Maximum time
C. Maximum cost
D. Minimum cost
✔ View Answer