Estimation And Costing In Civil Engineering objective questions and answers


21.  Annual repair estimate is usually not allowed to exceed


   A. 10% of capital cost

   B. 5% of capital cost

   C. 2% of capital cost

   D. .5% of capital cost


✔ View Answer


C. 2% of capital cost

✍ Your Comments

Your name:

Your Email:

Your Comments:



22.  Lead and lift is the term used in


   A. Earth work

   B. Reappropriation of funds

   C. Salvage value

   D. Tender notifications


✔ View Answer


D. Tender notifications

✍ Your Comments

Your name:

Your Email:

Your Comments:



23.  The life of a structure with brickwork in a lime or cement is taken as


   A. 100 years

   B. 35 years

   C. 50 years

   D. 25 years


✔ View Answer


C. 50 years

✍ Your Comments

Your name:

Your Email:

Your Comments:



24.  The life of teakwood doors and windows is usually take as


   A. 100 years

   B. 80 years

   C. 75 years

   D. 40 years


✔ View Answer


B. 80 years

✍ Your Comments

Your name:

Your Email:

Your Comments:



25.  The duet metal work is measured in


   A. Running metres

   B. Square metre on the basis of surface area

   C. Cubic Metres

   D. Kilograms


✔ View Answer


C. Cubic Metres