Estimation And Costing In Civil Engineering objective questions and answers
21. Annual repair estimate is usually not allowed to exceed
A. 10% of capital cost
B. 5% of capital cost
C. 2% of capital cost
D. .5% of capital cost
✔ View Answer
C. 2% of capital cost
✍ Your Comments
22. Lead and lift is the term used in
A. Earth work
B. Reappropriation of funds
C. Salvage value
D. Tender notifications
✔ View Answer
✍ Your Comments
23. The life of a structure with brickwork in a lime or cement is taken as
A. 100 years
B. 35 years
C. 50 years
D. 25 years
✔ View Answer
✍ Your Comments
24. The life of teakwood doors and windows is usually take as
A. 100 years
B. 80 years
C. 75 years
D. 40 years
✔ View Answer
✍ Your Comments
25. The duet metal work is measured in
A. Running metres
B. Square metre on the basis of surface area
C. Cubic Metres
D. Kilograms
✔ View Answer
✍ Your Comments