Survey - Survey In Civil Engineering objective questions and answers
1. The surveying used to determine additional details such as boundaries of fields, is called
A. City surveying
B. Location surveying
C. Cadastral surveying
D. Topographical surveying
✔ View Answer
✍ Your Comments
2. The vertical distance between any two consecutive contours is called
A. Vertical equivalent
B. Horizontal equivalent
C. Contour interval
D. Contour gradient
✔ View Answer
✍ Your Comments
3. The principle of tacheometry is used
A. For locating contours
B. On hydrographic survey
C. For filling in detail in topographic surveys
D. All of the above
✔ View Answer
✍ Your Comments
4. The limiting length of the offset is ........... when its perpendicular direction is set out by an eye
A. 5 m
B. 10 m
C. 15 m
D. 20 m
✔ View Answer
✍ Your Comments
5. The curve used for ideal transition curve is a
A. Cubic parabola
B. Clotroid spiral
C. Cubic parabola
D. Lemniscate
✔ View Answer
✍ Your Comments