Sewage Treatment Plant objective questions and answers
16. Which operation is generally not done during preliminary treatment of sewage
A.Chlorination of sewage
B.Oil and grease removal from skimming tanks
C.Removal of grit
D.removal of sand
✔ View Answer
A. Chlorination of sewage
✍ Your Comments
17. Lead acetate test in seewer manhole is done to test the presence of
A.Methane
B.Hydrogen sulphide
C.Carbondioxide gas
D.Diesel vapours
✔ View Answer
✍ Your Comments
18. The suitable cross-section of sewers to carry combined flow, is
A.Circular
B.Egg shaped
C.Rectangular
D.Horse shoe shaped
✔ View Answer
✍ Your Comments
19. The laying of sewers is done with
A.Magnetic compass
B.Theodolite
C.Level
D.Plane table
✔ View Answer
✍ Your Comments
20. In R.C. sewer pipes, the percentage longitudinal reinforcement to the cross-sectional area of cencrete is kept
A.10.0
B.5.0
C.2.0
D.0.25
✔ View Answer
✍ Your Comments