Estimation And Costing In Civil Engineering objective questions and answers
1. Which estimate is expected to be least accurate?
A. Preliminary estimate
B. Plinth area estimate
C. Detailed estimate
D. Revised estimate
✔ View Answer
B. Plinth area estimate
✍ Your Comments
2. A revised estimate is usually prepared when the original estimate has exceeded by more than
A. 1%
B. 2%
C. 10%
D. 100%
✔ View Answer
✍ Your Comments
3. The person who enjoys the estimate right is called a
A. Lesser
B. Lesse
C. Dominant owner
D. Servient owner
✔ View Answer
✍ Your Comments
4. Annual repair estimate is usually not allowed to exceed
A. 10% of capital cost
B. 5% of capital cost
C. 2% of capital cost
D. 5% of capital cost
✔ View Answer
✍ Your Comments
5. Which of the following is necessarily an accurate estimate?
A. Plinth area estimate
B. Cubical content estimate
C. Revised estimate
D. None of the above
✔ View Answer
✍ Your Comments