Railway Engineering - Railway Engineering objective questions and answers
11. The check rails are placed opposite the crossing so that
A. It is symmetrically placed opposite nose of crossing
B. Its one third length is ahead of the nose of crossing
C. Its two third length is ahead of the nose crossing
D. Its three fourth length is ahead of the nose of crossing
✔ View Answer
C. Its two third length is ahead of the nose crossing
✍ Your Comments
12. A triangle of railway consists of
A. Three turnouts
B. One turnout and two diamonds
C. Two turnouts and one split
D. One turnout, one split and one diamond
✔ View Answer
✍ Your Comments
13. Rail tops of a track are placed
A. At an inward slope of 1 in 20
B. At an outward slope of 1 in 20
C. At an inward slope of 1 in 30
D. At an outward slope of 1 in 30
✔ View Answer
✍ Your Comments
14. Arrangement made to divert the trains from one track to another is known as
A. Railway point
B. Railway crossing
C. Turnout
D. Railway Junction
✔ View Answer
✍ Your Comments
15. The force which resists the forward movement and speed of train is called
A. Friction
B. Tractive resistance
C. Hauling resistance
D. Track modulus
✔ View Answer
✍ Your Comments